Vilecha PV Plants evacuation line



DESCRIPTION
Construction of the buried 30 kV medium-voltage evacuation line to connect the Fenera, Roteles, Valtarafon, and El Monte photovoltaic plants to the Vilecha 132/30 kV substation.
The total length is 8.52 kilometers and runs in six different sections depending on the number of circuits. The final section totals eight, carrying a nominal power of 172.4 MVA. Each circuit uses 18/30 kV HEPERZ1 1x630KAl+H25 conductors.
There are several intersections along the route with national highways and municipal water supply pipelines, which have been overcome by directional drilling and reinforced crossings.