MARACOF OUR PROJECTS

Home / Projects / Mudarra I & II PV Plants

Mudarra I & II PV Plants

Year: 2025
Client: Abei Energy
Localización: España

DESCRIPTION

A set of two photovoltaic plants built during 2025, with total capacity of 130,34 MW. The scope of work includes access and security control, site facilities, complete civil works, module installation, and electrical installation.

The plots occupies 203.22 hectares, with 11.4 km of fencing, 9.5 km of roads, 4.8 km of ditches, 13 foundations for transformer stations, and 50,000 m of low voltage, medium voltage trenches and CCTV. A total of 228,720 modules, 969,000 m of solar cable, 179,000 m of LV aluminum cable, and 24,300 m of LV aluminum cable will be installed.

The plants will be completed by November 2025.